Back to the notes

Notes

Multi-region SD-WAN rollout across APAC and EMEA branches

Turning an SD-WAN decision that lived in a slide deck into branches that actually came up, wave by wave, across two operating regions.

Situation

The branch estate had grown site by site over several years, and the WAN had been assembled the same way: a primary circuit per site, a backup that had never actually been failed over, and a routing design that treated every site as a special case. The SD-WAN platform itself was already a corporate-standard decision, so my job was not a product bake-off. It was the harder, less visible part — making a decision that already existed on paper survive contact with live branches across two regions and a great many time zones.

Approach

I did not treat it as a device rollout. I treated it as three problems that can be verified separately: the quality of the underlay circuits, the control plane of the overlay, and the path packets actually take. Passing any one of those proves nothing about the other two, so each site had to produce its own evidence for each. I also deliberately inverted the migration order: the first template came from the most boring, least contentious site rather than from the most important one everybody was watching.

What I actually did

  • Captured the current state per site before editing anything: running config, routing adjacency state, route counts, interface error counters, and the NAT and ACL behaviour people depended on but had never written down.
  • Built the overlay at the pilot site, then verified control plane and data plane separately. An adjacency coming up is not the same thing as traffic following the intended tunnel, so I checked both and put the actual commands in the change record.
  • Application-aware policy: mapped the application classes first, then confirmed the real path in the forwarding table and the per-tunnel statistics rather than trusting a green result in the policy view.
  • Per-tunnel QoS: voice and interactive classes into the priority queue, batch and backup traffic policed into what was left, with confirmation that each policy was attached to the correct interface and direction.
  • Ran forced failovers by actually shutting the primary circuit at an agreed hour, so the backup was tested rather than assumed.
  • One change record per site: pre-checks, the validation command list, the exact back-out steps, and how the management route (console or out-of-band) would stay reachable.
  • Kept an observation period between waves and recorded every site’s validation in one shared format, so management and first-line support were reading the same picture.
  • Prove the underlay before the overlay: latency, jitter and loss baselines per circuit, because otherwise every later complaint of ‘it got slow’ has nothing to be measured against.
  • Pilot one real site, in production, with that site’s business users informed — rather than declaring success in a lab.
  • Collapse the design into a repeatable template: addressing, routing, application classes, QoS policy, naming and comments all fixed, so site ten looks like site one.
  • Keep the old WAN path warm until each site earns its keep, so a single-site revert is a boring event rather than an incident.

Outcome

Once the template site held, adding a site stopped being a custom configuration project and became a parameter fill plus a validation run. The more useful change was in the questions: we went from ‘is the network down’ to ‘which class did this application land in, which tunnel is it using, and does that tunnel still have headroom’. The second kind of question can be answered; the first one cannot. No lengthily reported service interruption landed during the migration — problems stayed inside their own wave.

What I would do differently

I would bring the application owners in much earlier to define the class list together. An application-class list reverse-engineered from tickets will always miss the internal application nobody reports that stops a warehouse when it breaks. I would also finish the underlay quality baseline on the EMEA side before the first wave: circuit quality differs a lot between the two regions, and early on I filled that gap with assumption.