Building a plant network from nothing — wired, wireless and firewall

A from-nothing campus build: three irreconcilable traffic types — production, warehouse and office — sharing one backbone and one egress.

Situation

This is a greenfield build I worked on while I was at SYSTEX: a brand-new plant needed its network from nothing, covering wired, wireless and firewall. The difficulty was not any single technology. It was that the campus had to host three kinds of traffic with nothing in common — production-line equipment wanting stability and predictability, warehouse scanners wanting roaming and capacity, and office wanting flexibility and easy support — all sharing one backbone and one egress. Add the requirement every manufacturer has: equipment vendors need remote support access, which is precisely the path that gets opened permanently and becomes a security finding years later.

Approach

I started from requirements rather than an equipment list: cut the campus into production, warehouse and office, ask what each one cares about and who should not be able to talk to whom. On wireless I insisted on coverage-and-capacity design instead of converting budget into an access-point count, because metal racking, machinery and traffic routes in a plant all eat signal. Firewall policy got organised by trust zone: production-to-office, office-to-internet and vendor-to-production are three separate questions and should not be answered with one mixed rule table.

What I actually did

  • Wrote the zone names and requirements down with the customer: which devices count as production, which are shared, which must be fully separated — with an owner signing it.
  • Built the racks, patching and wired access layer: uplink planning, PoE capacity calculation for access points and cameras, and interface descriptions and labels filled in properly, because the person maintaining this in two years will not be me.
  • Deployed wireless from a real site survey: walked coverage on foot, checked roaming behaviour against actual scanner paths, and reduced SSID-to-VLAN mapping to a table. Enterprise authentication rather than a shared passphrase.
  • Designed firewall rules per trust zone with source, destination, application and port narrowed as far as the requirement allowed — starting at least privilege and widening later on observed traffic, rather than opening first and tightening never.
  • Designed vendor remote support as controlled access: limited source and destination, auditable, time-boxed, with the request and revocation process written into the documentation.
  • Ran three test suites after build: wired failover (physically pulling the cable), wireless coverage and roaming walk-tests, and firewall rule verification using real requests to confirm both what was allowed and what was denied, and why.
  • Closed with acceptance against the agreed test items, drawings and interface mappings updated to match reality, and a session with the customer’s operations team on daily operation and the order to check things in when something misbehaves.
  • Test everything possible before site go-live, so the on-site day only repeats known results.

Outcome

All three parts passed acceptance against the pre-agreed items, including a pull-the-cable failover drill and rule-hit verification with real traffic. Cross-zone access now requires an explicit allow rule, so production no longer shares a trust environment with office; vendor remote support became a controlled procedure with source limits, expiry and audit rather than an open path. No unplanned interruption affecting production was reported during the build and cut-over — for a new plant, that is the sentence that matters most.

What I would do differently

I would bring production and facilities in much earlier. The biggest variable in wireless planning is not technology, it is ‘in two weeks a machine goes where your access point was’. Changes in metal and traffic paths after the ceiling is closed are expensive to fix. I would also nail down the vendor remote-support requirement at the start instead of on the day the equipment arrives — because that is when a compromise is most easily made under pressure.